Where do I start a Pacific Palisades rebuild?

Use the City of Los Angeles process for a City parcel. The City lists coordinated rebuild centers at 1828 Sawtelle Boulevard and 16925 Marquez Avenue, with posted weekday hours of 9 a.m.–5 p.m. Prior permits, occupancy certificates, assessor and Coastal Commission records can establish the former building; photographs or LiDAR may be considered case by case. City of Los Angeles: Rebuilding resources

What to do: Gather the prior use, unit count, dimensions and records before choosing a route. For a Malibu parcel, use the Malibu guide.

Should I use EO1 or EO8 for my rebuild?

Ask Planning and LADBS whether EO1 or EO8 fits your proposed rebuild. EO1 covers eligible property substantially damaged or destroyed in the January 2025 City wildfires. Generally, keep the former use and primary-unit count, substantially the same location, and no more than 110% of former footprint and height. Multiple property types qualify; new ADUs have separate rules. Los Angeles City Planning: Palisades rebuild FAQ

It depends on: EO8, issued July 23, 2025, covers eligible zoning-compliant single-family Coastal Zone rebuilds, including projects larger than 110%. Keep the same primary-unit count; an eligible ADU is allowed. Lot consolidation, subdivision and lot-line adjustments are excluded. Stay at least 10 feet from canyon bluffs and 25 feet from coastal bluffs, and meet environmental protections. LADBS: EO1 implementation guidelines, June 11, 2026

Eligible EO1 rebuilds avoid specified environmental and coastal reviews, but building, fire, geology and technical reviews remain. Projects outside both routes need the usual approvals. The City and its ZIMAS property map help identify bluff and biological-resource requirements. LADBS: Rebuilding implementation guidelines

What to do: Get the route and remaining clearances confirmed on a site plan before pricing an expansion.

Can I keep old setbacks or use hillside relief?

Show LADBS the old and proposed setbacks before moving or enlarging the building. EO1 can preserve qualifying older setbacks and other conditions that do not meet today’s zoning rules. June 11, 2026 guidance requires expansion to meet current setbacks or qualifying existing older setbacks. Moving within an older setback cannot reduce the yard further or increase the building’s extent or height there. Los Angeles City Planning: Palisades rebuild FAQ

Eligible projects receive relief from specified hillside street-width, dedication and continuous-paved-road requirements. Specified relief also extends to zoning-compliant single-family rebuilds; sewer connections may remain required. Other hillside rules still apply. LADBS: EO1 implementation guidelines, June 11, 2026

What to do: Mark the old footprint, expansion, setbacks, access and sewer connection for LADBS review.

Can I add an ADU, or use SB 9?

Plan an eligible attached or detached ADU before or after the main rebuild under June 2026 EO1 guidance. State and local ADU rules apply. New ADUs are not automatically capped at 110% of an old accessory building; bluff restrictions may apply. LADBS: EO1 implementation guidelines, June 11, 2026

EO9 blocks City acceptance or processing of SB 9 lot-split/two-unit applications inside both the Palisades fire boundary and a Very High Fire Hazard Severity Zone. Qualifying vested, complete applications accepted before the Governor’s July 30, 2025 order have an exception. ADUs follow a separate route. City of Los Angeles: Recovery FAQ

What to do: Ask Planning to check both boundaries and any vested-application exception. See the Los Angeles ADU rules.

Which Los Angeles rebuilding fees are waived?

Check that you owned the entire site on January 7, 2025 before budgeting fee relief. The current waiver took effect July 16, 2026 after EO7’s earlier fee suspension; eligible earlier payments can be refunded. Selling before the occupancy certificate triggers repayment; later burned-lot buyers do not qualify. LADBS: Wildfire fee waiver effective July 16, 2026

It depends on: Eligible fees are offset through the amount attributable to 110% of the original structure’s area. LADBS charges for area above that threshold. The program has a $90 million total cap over three years. Get the area calculation in writing, especially for added stories. LADBS: Rebuilding and fee-refund FAQ

Request eligible refunds through the Palisades Wildfire Permit Fee Refund Portal, by mail or at the cashier counter. Each permit needs its own application, payment evidence and required acknowledgement. Los Angeles CAO: First Financial Status Report, rebuilding fee waiver

What to do: Confirm eligibility, remaining program capacity and charges with LADBS, then follow its current refund instructions.

How long does review take, and can my designer self-certify?

Choose a review method with your designer and track complete-submission dates. EO1’s summary directs complete-application review within 30 days and clearances within five days. Detailed Planning procedures specify five business days for certain clearances; corrections and other approvals can remain. LADBS: Rebuilding implementation guidelines

The March 3, 2026 pilot lets City-approved California architects and civil engineers certify qualifying EO1 single-family projects up to three stories. LADBS must confirm eligibility; some geologically sensitive sites are excluded. Other approvals, inspections, occupancy sign-offs, audits and enforcement remain. LADBS: EO1 implementation guidelines, June 11, 2026

City standard plans include homes and ADUs; designers own them and may charge. Site changes, final review, permits and inspections still apply. Eligible EO1/EO8 rebuilds generally must finish within three years after the building permit. Later orders, Council action and LADBS extensions under existing procedures can change that deadline. LADBS: Self-certification pilot guidelines, March 3, 2026

Los Angeles dates and review clocks
Date or periodWhat to track
July 16, 2026Current fee-waiver ordinance took effect.
30 days / five daysEO1 summary review/clearance directions; specified Planning clearances use five business days. Corrections and other approvals can remain.
Three years after building permitGeneral EO1/EO8 completion period, subject to later orders, Council action and LADBS extensions.

What to do: Get your permit’s actual expiration date and extension terms in writing.

What debris-clearance and soil records should I keep?

Retrieve the property’s government-program Final Sign Off or private-program permit closure. County reports government-sponsored Phase 2 cleanup finished in September 2025; that milestone does not establish clearance for each private-cleanup parcel. Debris final records

County’s private-cleanup protocol requires removing the upper six inches of soil in the ash footprint to visibly clean soil. Confirmation testing may be needed if cleanup proof is inadequate. It does not establish a universal City testing exemption. The County’s soil lead testing program transitioned to USC CLEAN on August 15, 2026; lead screening and engineering soil review are separate. LA County: 2025 wildfire private debris-removal FAQ

What to do: Ask the City which lot-specific acceptance documents and soil or geotechnical reports it requires.

What must I arrange with LADWP?

For temporary power, coordinate the meter/service location with LADWP. June 8, 2026 instructions require LADBS approval for overhead and underground temporary installations. LADWP’s neighborhood restoration and permanent undergrounding work are separate from an individual home’s service approval. LADWP: Requesting temporary power, June 8, 2026

LADWP lifted the Do Not Drink restriction on March 7, 2025 across all previously covered Pacific Palisades areas. Damaged private plumbing and meter reconnection remain separate. Ask for current parcel-specific water and power instructions. LADWP: Restoration and rebuilding efforts

What to do: Start utility coordination during design and record required inspections and service releases alongside your permit tasks.

Which building and brush-clearance rules remain?

Ask reviewers which code and landscape rules your property must meet. After January 1, 2026, N-37-25 lets qualifying residential rebuilds use the 2022 code while retaining specified 2025 fire/public-safety rules and flood elevations/certificates. Solar and battery installation relief keeps solar-ready duties. Governor: Executive Order N-37-25, November 24, 2025

LAFD requires year-round vegetation compliance on owners’ land in the City’s Very High Fire Hazard Severity Zone. It reaches 200 feet from buildings, including neighboring buildings, and 10 feet from combustible fences or roads/driveways. Burned lots can still have duties; this does not authorize clearing a neighbor’s land. LAFD: Brush clearance requirements

What to do: Confirm required construction and landscape inspections through occupancy. See the fire-rebuild guide for insurance, tax and contractor checks.

What else should I know?

Can a Pacific Palisades rebuild be larger than 110%?

EO8 provides a route for eligible zoning-compliant single-family Coastal Zone rebuilds, including larger projects; all eligibility conditions still apply.

LADBS: Rebuilding implementation guidelines

Link to this answer
Does self-certification remove inspections?

No. The City’s pilot retains other department approvals, construction inspections and occupancy sign-offs.

LADBS: Self-certification pilot guidelines, March 3, 2026

Link to this answer

Sources

What should I do next?

  1. Describe your fire-rebuild project, city, damage and current stage in the guided project search.
  2. Talk to Us about the decisions and documents you need to organize.

Sources checked on November 21, 2026. Rules can change and can differ by property; confirm details with the agency reviewing your project.