Who issues my fire-rebuild permit in Malibu?
Confirm the City boundary first: a Malibu mailing address can be outside City limits. Inside the City, Malibu coordinates rebuilding with LA County Fire and Waterworks. Malibu is entirely in the Coastal Zone, and its certified Local Coastal Program takes precedence over conflicting City zoning. City of Malibu: Rebuilding steps
The Rebuild Center is at 23805 Stuart Ranch Road, Suite 240; phone 310-456-2489 ext. 400. The April 27, 2026 guide lists weekday hours of 8 a.m.–4 p.m. City of Malibu: Start-to-finish rebuilding guide, April 27, 2026
What to do: Confirm the parcel boundary and begin with City Planning. Use the City of Los Angeles guide for a City of LA parcel.
Does my Malibu rebuild qualify for the coastal exemption?
Ask Planning to check floor area, height and bulk separately. The coastal exemption allows no more than 10% growth in each, with the same use and substantially the same location. Bulk means building volume; increasing height and area by 10% can exceed its limit. City of Malibu: Start-to-finish rebuilding guide, April 27, 2026
City policy requires meeting a 50% former-footprint/envelope location test. New basements and underground garages count toward the 110% square-footage limit. Palisades replacements cannot extend farther seaward than before the fire. Rules on neighboring buildings’ projections and oceanfront alignment also govern moving space toward the ocean.
What to do: Show old and proposed footprint, envelope, area, height, bulk and seaward edge for Planning Verification.
When would I need a Coastal Development Permit?
Ask which coastal route your design needs before setting a schedule. Projects more than 10% larger or in a new location generally need a Coastal Development Permit (CDP). Some moves qualify for a limited de minimis waiver if specific findings are met. City of Malibu: Rebuilding options
Added area above 18 feet, on slopes steeper than 3:1 or in setbacks may need Administrative Plan Review and Site Plan Review. The April 27, 2026 guide allows 10 business days per Planning Verification review. The options page estimates three to six months for administrative/site-plan review and 12 to 24 months for a CDP. Corrections, notices, appeals and building review add time. City of Malibu: Start-to-finish rebuilding guide, April 27, 2026
What to do: Get Planning’s route decision and current timing estimate before finalizing the design.
What geology work and foundation checks are required?
Ask a geotechnical consultant to review your site and foundation plan before budgeting reuse. The City’s guidelines date from July 13, 2026, with a July 16 checklist. Every Palisades/Franklin rebuild site needs code evaluation. City of Malibu: Fire rebuild geotechnical guidelines, version 2, July 13, 2026
Reliable existing information can help. Deep foundations or inadequate hazard/design information require a comprehensive report. Limited reports cover only qualifying single-family, like-for-like Planning Verification–Palisades Fire projects with adequate information and suitable foundations. Beachfront properties and other excluded types need comprehensive reports. City of Malibu: Foundation reuse
Unresolved geologic hazards may require a recorded Assumption of Risk and Release. Foundation reuse needs feasibility review, then building-plan review, engineering/testing and evaluation of the foundation and bearing soils. Feasibility acceptance permits plan submission; reuse can still be rejected. Timber piles cannot be reused.
What to do: Give the consultant prior reports and obtain City direction before assuming foundations can stay.
Can I reuse my septic system after the fire?
An onsite wastewater treatment system (OWTS), often called a septic system, needs assessment by a City-registered inspector and City approval before reuse. Malibu requires advanced systems for beachfront, multifamily and commercial properties previously using conventional systems. A system with all components damaged or failing may also need replacement. City of Malibu: Onsite wastewater treatment systems
New-system design needs bedroom/fixture counts, a scaled plot plan, percolation/soil information and supporting geology. Beachfront systems also need a coastal engineer’s wave-uprush report. Malibu’s rebuilding steps require an OWTS operating permit within 60 days after the Certificate of Occupancy for rebuilt Palisades/Franklin properties. City of Malibu: Onsite wastewater treatment systems
What to do: Arrange the inspection before fixing the bedroom count and site layout; track the separate operating-permit deadline.
Who qualifies for Malibu’s fire-fee waiver?
Check the fire, residence date and ownership conditions before relying on Malibu’s waiver. Qualifying owner-primary-residence homes damaged by Palisades, Franklin or Broad can receive the like-for-like/plus-10% City waiver. The residence dates are January 7, 2025; December 9, 2024; and November 6, 2024, respectively. City of Malibu: Fire rebuild fee waiver
It depends on: Both duplex units must be owner-occupied primary residences, and both owners must qualify. Commercial rebuilds are excluded. Apply by 4 p.m. June 30, 2028; Planning must deem the application complete by June 30, 2028. Obtain all required building permits by December 30, 2030; later permits carry full fees. LA County Fire: Malibu fee waivers and refunds
Two affidavits document eligibility and recorded conditions. Eligible City septic-system, accessory, landscape and temporary-housing fees are included. Selling before occupancy triggers repayment; post-approval revision fees are excluded.
LA County Fire offers a separate waiver/refund for eligible Malibu owner-occupied single-family Palisades rebuilds. It uses City eligibility verification.
| Date or period | What to do |
|---|---|
| 4 p.m. June 30, 2028 | Submit an eligible fire-fee waiver application. |
| June 30, 2028 | Have the planning application deemed complete for fee relief. |
| December 30, 2030 | Obtain all required building permits for fee relief. |
| January 7, 2031 / January 7, 2033 | For January 7, 2025 damage, generally start planning within six years and obtain a permit within eight to preserve qualifying older conditions. Diligent pursuit and an unexpired permit are required. |
| 60 days after occupancy certificate | Obtain the septic operating permit for rebuilt Palisades/Franklin properties. |
What to do: Get written eligibility, recorded conditions and remaining charges from the City.
How long do I have to preserve old nonconforming conditions?
Track the separate deadlines for preserving older setbacks or heights that do not meet today’s rules. Generally, begin disaster-rebuild planning within six years and diligently pursue and obtain a building permit within eight years. Keep the permit from expiring; Planning Commission hardship extensions require specific findings. City of Malibu: Disaster rebuild deadlines
For January 7, 2025 damage, the anniversaries are January 7, 2031 and January 7, 2033. Fee-waiver deadlines come earlier under a separate program. City of Malibu: Start-to-finish rebuilding guide, April 27, 2026
What to do: Confirm the recognized damage date, proof of planning start and permit deadlines with Planning.
What debris, fire and utility approvals remain?
The original government cleanup election deadline was April 15, 2025. Malibu’s private-cleanup deadlines were June 1, 2025 to secure a debris permit and contractor and June 30, 2025 to finish; these are historical dates. Retrieve the individual lot’s Final Sign Off or private permit closure rather than treating mission completion as parcel clearance. County debris-removal gateway
County’s private-cleanup protocol uses a six-inch ash-footprint soil removal to visibly clean soil, with possible testing where cleanup proof is inadequate. City acceptance and geotechnical requirements must be checked separately. LA County: 2025 wildfire private debris-removal FAQ
Arrange early LA County Fire site review for access and constraints. Building, mechanical, electrical, plumbing and septic permits are typical, and Pacific Coast Highway work may require a Caltrans encroachment permit. Malibu coordinates with County Fire and Waterworks for its City rebuilds. City of Malibu: Rebuilding steps
What to do: Ask the City for a written clearance list, then coordinate Fire, water and other utilities against the same site plan.
Does Malibu’s SB 9 restriction also ban ADUs?
Malibu’s October 15, 2025 policy says the City will not process SB 9 applications within the Palisades fire area’s Very High Fire Hazard Severity Zone. It concerns lot splits and two-unit projects, not a blanket ADU prohibition. City of Malibu: Start-to-finish rebuilding guide, April 27, 2026
What to do: Ask Planning to check the parcel and any vested-application issue. Use the Malibu ADU rules page for related ADU planning and the fire-rebuild hub for insurance and contractor checks.
What else should I know?
Does a new Malibu basement count toward the 110% rebuild limit?
Yes. New basements and subterranean garages count toward Malibu’s 110% rebuild square-footage limit.
City of Malibu: Start-to-finish rebuilding guide, April 27, 2026
Link to this answerDoes a surviving septic tank mean I can reuse the system?
No. A City-registered inspector must assess the OWTS and the City must approve reuse.
City of Malibu: Onsite wastewater treatment systems
Link to this answerSources
- City of Malibu: Start-to-finish rebuilding guide, April 27, 2026
- City of Malibu: Fire rebuild fee waiver
- City of Malibu: Rebuilding steps
- City of Malibu: Rebuilding regulations, policies and guidelines
- City of Malibu: Rebuilding options
- City of Malibu: Fire rebuild geotechnical guidelines, version 2, July 13, 2026
- City of Malibu: Foundation reuse
- City of Malibu: Onsite wastewater treatment systems
- LA County Fire: Malibu fee waivers and refunds
- City of Malibu: Disaster rebuild deadlines
- County debris-removal gateway
- Malibu debris removal
- Debris final records
- LA County: 2025 wildfire private debris-removal FAQ
Sources checked on November 21, 2026. Rules can change and can differ by property; confirm details with the agency reviewing your project.